ContractsFFor FreelancersBeginner

The Risk of Working Without a Contract

Specific risks faced by freelancers who accept work based on verbal agreements alone - including unpaid fees, scope expansion, and ambiguous responsibilities - and how to address them

"Contracts are unnecessary because we have a trust relationship" and "complicated procedures can be handled later"—freelancers who make such judgments and accept work without contracts continue to find themselves embroiled in serious troubles.

Web designer Mr. Tanaka (pseudonym) was promised ¥300,000 in compensation for a corporate website creation project he received through an acquaintance's introduction, based on verbal agreement alone. However, after delivery, the client refused payment claiming it was "different from what they had imagined." They demanded revisions, but there were no agreements on what constituted free support, what the criteria for additional charges were, or anything else. As a result, he continued working without compensation for three months and ultimately received only ¥100,000.

Writer Ms. Sato (pseudonym) accepted a request for "light article creation for about one week," but was actually asked to conduct continuous interviews and writing for three months. The interpretation of "light work" differed greatly from the client's expectations, but without a contract, she couldn't clearly assert the scope of work and ended up spending ten times the initially anticipated effort.

These are by no means rare cases. Surveys show that about 60% of freelancers who accept work without contracts experience some form of condition disagreement or trouble. Let's examine from a practical perspective why these problems occur and how they can be prevented.

Five Risks of Working Without Contracts

This section reveals the specific problems that actually occur with verbal outsourcing agreements and their severity.

1. Risk of Unpaid or Reduced Compensation

The most serious issue is trouble related to compensation. Without a contract, "promised compensation amount," "payment conditions," and "payment deadlines" tend to become ambiguous.

Let's look at a specific case. Graphic designer Mr. A accepted a flyer design job with a verbal promise of "¥50,000." However, upon delivery, the client argued "I thought ¥50,000 included revisions" and "the budget has become tight, so please make it ¥30,000." Without written evidence, he had no choice but to accept the loss.

According to surveys on compensation troubles for freelancers, the incidence rate of unpaid or reduced compensation for work without contracts is about 23%. This is nearly six times higher than cases with contracts (4%). In terms of amounts, cases without contracts often have to accept an average reduction of about 40%.

2. Unlimited Expansion of Work Scope

There's a high risk of being asked to perform work far beyond initial expectations through ambiguous expressions like "just a small addition" or "minor revision."

In a web writer's case, a request for "one 3,000-character article" actually expanded to include:

  • 3,000-character article body
  • Additional headline and subtitle suggestions
  • Outline creation for five related articles
  • Contacting and scheduling interviews with subjects
  • Photography and image selection
  • Summary text creation for social media posts

This required five times the initially expected effort, but no additional compensation was paid as it was considered "part of article creation." This is a typical example of outsourcing contract risks without documentation.

3. Excessive Burden Due to Ambiguous Responsibility Scope

When problems occur with deliverables, it becomes unclear how much is the contractor's responsibility. This is particularly serious in system development, where unlimited revision support may be demanded for reasons like "it doesn't work" or "it's not as expected."

Programmer Mr. B accepted an e-commerce site construction project for ¥600,000, but the following problems occurred:

  • Temporary shutdown due to server failure → "Take responsibility for the site being unusable"
  • Performance degradation from unexpected access concentration → "Speed it up for free"
  • Product data defects on the client side → "Data correction should be included in your response"

Problems that could have been avoided by clarifying responsibility scope in a contract all became the contractor's burden.

4. Unilateral Changes to Deadlines and Schedules

Sudden deadline changes due to client convenience and schedule pressure from delayed interim confirmations also occur frequently.

In a designer's example:

  • Original two-week production period → shortened to three days with "urgently needed by next week"
  • One month of neglect during interim confirmation → sudden urging with "delivery next week after all"
  • Major rework due to specification changes → unreasonable demands with "the deadline cannot be changed"

In cases where freelancers lack contracts, it becomes difficult to object to such changes.

5. Unreasonable Intellectual Property Demands

Without prior agreement on rights relationships for deliverables, there's a risk of being asked for excessive rights transfers.

In a photographer's case who contracted for photo shooting:

  • Photography fee: ¥100,000 (one-day shoot)
  • Later demanded "transfer copyright of all photographed images"
  • Refused additional payment claiming "it should be included in the photography fee"
  • Unlimited commercial use and secondary use also demanded

While proper copyright transfer fees are typically 2-3 times the photography fee, the lack of prior agreement resulted in lost negotiating power.

Why Contract-Free Work Emerges

This section analyzes the structural background that causes freelancers to neglect the necessity of contracts.

Japan's Unique "Trust-First" Business Customs

Japanese business culture has a strong tendency to value "trust relationships over contracts." The misconception that "requesting a contract = not trusting the other party" is deeply rooted, especially in transactions with small and medium enterprises and individual business owners.

Examples of actual client comments:

  • "We've always valued long-term relationships, so contracts are unnecessary"
  • "No need for such formalities"
  • "If there's a trust relationship, there are no problems"

However, trust relationships and contracts are not opposing concepts. Rather, contracts are tools that strengthen trust relationships by clarifying mutual understanding.

Urgency for Project Acquisition and Weak Bargaining Position

Freelancers have low income stability, creating psychology that doesn't want to lose immediate opportunities. Contract creation tends to be postponed especially in the following situations:

  • Project offers during financially difficult months
  • Urgent requests from major clients
  • "Leave it to us" responses for acquaintance/referral projects
  • Projects with intense price competition with competitors

Many freelancers think "requesting a contract will lose the project" due to their weak position, but actually, appropriate contract presentation often leads to higher evaluation of professionalism.

Hassle and Cost Burden of Contract Creation

Many freelancers think "contract creation is troublesome and expensive." Certainly, hiring lawyers incurs the following costs:

  • Contract creation fees: ¥50,000-200,000
  • Legal checks: ¥30,000-100,000
  • Attendance at contract negotiations: ¥20,000-50,000 hourly rate

However, simple contracts can actually be created by yourself, and templates can significantly reduce effort. Even for small projects, simply documenting minimum agreement items dramatically reduces trouble occurrence rates.

Familiarity and Complacency with Ongoing Projects

With continuing transactions with the same clients, complacency develops thinking "it's been fine so far." However, troubles occur due to changes such as:

  • Staff changes on the client side
  • Deterioration of company management conditions
  • Changes in project scale and importance
  • Budget pressure from market environment changes

Ongoing projects especially require periodic contract reviews to respond to relationship changes.

Practical Contract Creation Procedures

This section presents a step-by-step approach to contract creation that freelancers can actually use.

Step 1: Organizing Minimum Agreement Items

First, regardless of how small the project, always document the following five items:

Basic Five Items

  1. Work content (specific deliverables and scope)
  2. Compensation amount (tax-inclusive/exclusive specification and payment conditions)
  3. Delivery dates (interim confirmation schedules and final delivery dates)
  4. Revision support (number and scope of free revisions, additional charges)
  5. Rights relationships (copyright and usage rights attribution)

Even just confirming these via email significantly reduces the risks of verbal outsourcing agreements.

Email Confirmation Example

Subject: [Confirmation] Conditions for ○○ Production Project

Thank you for your continued support.
Please confirm that there are no discrepancies in your understanding
regarding the following conditions for the project we discussed recently.

■ Work Content
・Corporate website top page design (PC/mobile compatible)
・Design for 3 sub-pages
・HTML/CSS coding

■ Compensation and Payment Conditions
・Total: ¥300,000 (excluding tax)
・Payment: Bank transfer within 30 days of delivery confirmation

■ Delivery Schedule
・Design first draft: [Date]
・Coding completion: [Date]

■ Revision Support
・Design revisions: Up to 2 times free
・3rd time onward: ¥10,000 per revision

If these conditions are acceptable, please reply confirming your "acceptance."

Step 2: Creating Simple Contracts

Once agreement on the basic five items is reached, create a more detailed simple contract. Include the following items in 1-2 A4 pages:

Simple Contract Structure Example

  1. Parties (basic information of client and contractor)
  2. Work content (detailed specifications and deliverables)
  3. Compensation and payment (amount, method, deadlines)
  4. Delivery and progress (schedule and confirmation methods)
  5. Revisions and changes (scope, fees, procedures)
  6. Intellectual property rights (copyright and usage rights handling)
  7. Responsibility and exemption (warranty and damage compensation scope)
  8. Contract termination (midterm cancellation conditions and settlement methods)
  9. Confidentiality (information handling)
  10. Other (governing law, jurisdiction, etc.)

Step 3: Development into Formal Contracts

When project scale increases or continuous business relationships develop, more comprehensive contracts become necessary. Consider creating formal contracts based on the following criteria:

Cases Requiring Formal Contracts

  • Projects with total compensation exceeding ¥1,000,000
  • Long-term projects exceeding 3 months production period
  • Large projects divided into multiple phases
  • Projects handling confidential information
  • Projects involving multiple stakeholders
  • Projects including continuous maintenance and operation

Formal contracts specify risk allocation, damage compensation limits, force majeure clauses, governing law, etc., in more detail.

Step 4: Utilizing Contract Templates

Since creating from scratch each time is inefficient, prepare industry-specific templates.

Web Development Template Elements

  • Compatible browser and device specifications
  • Responsibility allocation for material provision
  • Server and domain management divisions
  • SEO optimization scope
  • Post-launch support content

Design Creation Template Elements

  • Provided data formats and resolution
  • Color proofing and print attendance requirements
  • Secondary use and modification permissions
  • Copyright notice methods
  • Rights relationships for awards and publications

Writing Template Elements

  • Interview presence and transportation cost burden
  • Number of proofreading and editing rounds
  • Citation and reprint permission scope
  • Byline and credit notation
  • Archive and reuse rights

Step 5: Contract Conclusion Practice

Once the contract is ready, conclude it through proper procedures:

  1. Prior explanation: Explain contract content verbally and resolve questions
  2. Revision response: Flexibly respond to modification requests from the other party
  3. Final confirmation: Clearly confirm both parties agree to the content
  4. Signature and seal: Create two originals for each party to retain
  5. Electronic contracts: Utilizing DocuSign, CloudSign, etc. is also effective

Pitfalls of Contract Neglect

This section points out common misconceptions about contracts and easily overlooked points that freelancers tend to fall into.

Overconfidence in "Email Records Are Sufficient"

Many freelancers think "contracts are unnecessary because we have email exchanges." While emails are indeed a form of written contract, they have the following limitations:

Problems with Email Agreements

  • Conditions scattered across multiple emails, unclear overall picture
  • Ambiguous expressions like "understood" or "leave it to us"
  • Missing or overlooked important items
  • Later interpretation differences saying "that's not what I meant"
  • Unclear relationships with attached files

In an actual trouble case, despite over 20 email exchanges, the crucial compensation amount and payment deadline remained ambiguous, resulting in a 3-month payment delay.

Poor Judgment on Acquaintance and Friend Projects

The casual judgment that "acquaintances are safe" is most dangerous. Rather, acquaintance projects tend to have more serious troubles for the following reasons:

  • Difficulty bringing up money discussions
  • Hard to present strict conditions
  • Unable to assert strongly when problems occur
  • Repeated compromises out of consideration for relationships
  • Difficulty taking legal action

Requests from acquaintances especially should clarify contract conditions to protect relationships. The attitude "precisely because we're friends, let's do this properly" is important.

Missing Contract Updates for Ongoing Projects

With continuing transactions with the same clients, the conditions from the first project often continue to be applied. However, condition reviews become necessary due to the following changes:

Changes Requiring Reviews

  • Work complexity and sophistication increases
  • Market price fluctuations
  • Personal skill improvement and track record growth
  • Organizational changes on client side
  • Legal and regulatory changes

Propose contract content reviews about once a year and adjust conditions to match current situations.

Contract Neglect for Small Projects

Many cases skip contract creation thinking "it's just a small ¥50,000 job." However, the following risks remain the same for small projects:

  • Possibility of unpaid compensation (regardless of amount)
  • Additional work occurrence
  • Delivery troubles
  • Excessive demands for deliverables

Rather, small projects tend to have higher trouble occurrence rates because clients' awareness is also lighter. Regardless of amount size, document minimum agreement items.

Excessive Focus on Contract "Format"

The misconception that "contracts must be impressive documents" is also problematic. What's important is content, not format, keeping the following points in mind:

  • Simple one-page A4 contracts have the same legal effect
  • Handwritten versions are valid (though readability is important)
  • Stamp tax varies by contract amount, but ¥200 for most projects
  • Electronic contracts have equivalent legal effect
  • What's important is that both parties' agreement content is clear

Rather than aiming for perfection, start by documenting basic agreement items.

Optimistic View of "We'll Think About It If Troubles Arise"

The thinking "we'll deal with problems when they occur" is unrealistic for the following reasons:

Difficulties of After-the-Fact Response

  • Difficult to prove without documentary evidence
  • Memory and testimony become ambiguous over time
  • Emotional conflicts make resolution difficult
  • Cost and time burden of legal procedures
  • Negative impact on reputation and credibility

Resolution costs after troubles occur are often more than ten times the cost of prior contract creation.

Contract Management Freelancers Should Practice Immediately

To avoid the risks of working without contracts, practice the following actions starting today.

First, review the contract status of all currently ongoing projects. For projects without contracts, definitely document agreements starting with the next similar project at the latest. Even for existing projects, reorganize agreement items when additional work or condition changes occur.

Next, prepare three types of contract templates suitable for your work content (simple, standard, detailed versions). By using them according to project scale, you can set appropriate contract conditions without excess or deficiency.

What's important is having the awareness that "contract creation = professional basics." Appropriate contracts not only protect yourself but also strengthen trust relationships with clients and create better work environments.

Don't underestimate the risks of outsourcing work without contracts, and make contract creation a standard business process starting from this very moment. That's the first step toward sustainable freelance activity.

Related Articles